Tendering Documents For Detached Bungalow: 1489240

  1. Three methods of approximate estimating

Accurate estimation helps project managers and clients to efficiently plan on where and how to get and utilize the resources needed to complete the project within the planned time and budget (Ji, et al., 2019). Some of the methods used in approximate estimating of building or construction projects are discussed below

  1. Analytical, deterministic or bottom-up estimating

This method involves identifying each separate activity that is needed to complete the project, breaking down these activities into smaller ones (lowest level of detail possible) and approximating the resources (financial, materials, equipment and labour), time and cost needed to complete each of these sub-activities. The project’s detailed estimate is them determined by adding up the activity totals. This method of approximate estimating should be used when the fine details of the project components and/or programme are known and well defined. This method may consume more time to complete but it is more accurate than comparative or parametric estimating.

  1. Analogous, top-down or comparative estimating

This method involves comparing known measures of resources and time that were used or needed to complete similar past or completed activities or project with those of the current project and use expert judgement to estimate the cost of the project. The method relies more on past experience in lieu of opinion but for it to be useful, there has to be definite similarity between the past and current projects that are being compared. For this method to be used, adequate information of the past project should be available. This information is then scaled down or up so as to meet the needs or description of the current project that is being estimated (2020ProjectManagement, 2020). This technique should be used when the information available about the project is limited hence its estimation is less accurate and less reliable.

  1. Statistical modelling or parametric estimating

This method involves analysis of technical, statistical, cost and programmatic data so as to determine the drivers or factors that influence cost and use them to develop cost models. The method develops the correlation between manpower and cost information with factors or constraints that describe the activity or task to be costed. In the process, a series of formulae or equations, referred to as cost estimation relationships (CERS), are drawn up and used to create outputs of cost for various components of the estimate. This method usually uses linear or non-linear (regression) analysis to establish the best algorithms for each of the cost models (Varghese and Kanchana, 2015). Parametric estimating method uses defined parameters that can be used to measure the project, such as cost or time that is needed to complete a particular deliverable of the project. This process is repeated for the different types of project deliverables and multiplied by the quantity of all the parameters needed to achieve the requirements of the project. For this technique to be used, it requires a significant amount of data about the project and its cost drivers.

  • Suitable form of tendering procedure

The form of tendering procedure plays a key role in successful completion of construction projects (Laryea, 2017). The project in this report involves construction of a two bedroom bungalow in Essex. The most suitable form of tendering procedure for this project is single-stage selective (competitive) tendering. This is a more radical tendering procedure than the other traditional methods. In this method, the client or employer identifies prospective competent contractors and issues them with an invitation to tender. The client can select the prospective contractors on advice from his/her professional team, including the consultant, quantity surveyor, architect or engineer, or from his/her own list of preferences based on referrals or having worked with them in the past. The preferred contractors must be suitable for a contract of that complexity, nature and size. The invitation to tender issued to prospective contractors contains full tender documents with all the necessary information of the project, such as relevant drawings, the scope of work, design of the project and bill of quantities. This information helps the contractors to understand the actual needs of the client and appreciate the levels of responsibilities of each party.

After preparing the tenders, the prospective contractors return them to the client. The client analyzes and compares the tenders together with his professional team and then selects the preferred tenderer. The commonly used criteria used to select the preferred contractor include: quoted contract price, past experience of similar projects, technical capacity (availability of equipment and technical staff), track record and reputation. The client then starts negotiating with the preferred contractor about the final price of the project before the contract is awarded. There must be a mutual agreement between the client and contractor before the contract is awarded and signed by the two parties. The method is applicable in contracts where all the necessary information is available to determine the realistic price of the project.

Some of the key advantages of single-stage selecting tendering procedure are: saves time, saves tendering costs, and bids are only received from capable contractors. Disadvantages of this tendering procedure include: there is less competition compared to open tendering, and it does not give a chance for new contractors who may be more capable of doing the job than the preferred contractors. With single-stage selecting tendering, clients feel more confidence that the successful contractor will be able to meet their needs.

Use of single-stage selective tendering procedure is becoming more common in the construction market due to greater certainty of the project’s final price and faster decision making, which are beneficial to both the client and the contractor. In single-stage selective tendering, the process is more simplified because a completed design is provided to the preferred contractors who are asked to bid for the project. Cost risk management is one of the main factors that are driving use of single-stage selective tendering. In this method, there is a minimal chance of contractors varying the price by a big margin or making claims since their bids are based on the detailed completed building design. Additionally, all the potential contractors prepare bids using a single source of tender documents.

In this scenario, the detailed design of the building has already been completed and tender documents prepared. The next step is for the client to identify the most suitable or competent contractor to actualize the project. It means that the client has already specified his needs and wants to involve the contractor in construction activities only. Single-stage selective tendering process will enable the client to select qualified contractors with the required experience, resources (financial, equipment and technical) and track record to complete the project. The procedure clearly allocates risk to each party and also speeds up the procurement process. This means that the project will start more quickly and be completed within shorter timeframes thus reducing timing and cost risks than when other tendering procedures were used, such as open tendering or two-stage tendering.

  • Suitable procedure to vet a contractor

Selection of a contractor is a very crucial process in ensuring successful implementation of any construction project. Therefore it is important to vet the contractor before awarding the tender. The vetting process involves performing a background check of the prospective contractor. As the client’s architect, vetting the contractor would involve use of the criteria below

Past and current performance: this information gives an idea of the type of projects that the contractor has been involved with in the past. Some projects are best done by contractors who have experience in executing similar projects (Belek, 2017). Generally, it is recommended to select a contractor who has completed similar projects before because they are more experienced on how to manage issues, such as complexity, resource management or disputes.

Workload: it is important to check the current and future workload of the contractor. This is so as to ensure that the contractor will give adequate attention to the project. Failure to allocate adequate attention, employees, equipment and other resources to the project can compromise the quality and speed of the project. The current workload of the contractor should not hinder project implementation.

Personnel: the contractor should have qualified employees with relevant academic qualifications (knowledge) and experience to complete the work. It is important to know the number of full-time, part-time, contract and casual employees. Where necessary, some employees should be licensed professionals and the workers should have the right tools for the job. The workloads for the employees must also be reasonable.

Technical capacity: besides qualified personnel, the contractor selected should have the required equipment and machinery to complete the project. The equipment can either be owned or leased, with proof (legal documents) to show the same.

Financial capacity: the contractor should also have adequate financial resources to start and complete the work. The contractor should have the financial capacity to pay staffs, lease equipment and purchase some materials without a struggle. This can be known by requesting for the contractor’s financial statements for at least two years, total sales or revenue and annual volume. Indicators such as declining income, big debts and poor cash flow are red flags.    

Accreditation and registration: the contractor selected should be accredited by the relevant government agencies and be in possessing of legal, valid and up-to-date documents, such as registration certificates and applicable practicing licenses.

Safety practices: this involves checking various measures that the contractor has put in place or systems they use to ensure safety of their employees and visitors on site. Some of the key items to look for include: training of employees on occupational safety and health practices, availability of personal protective equipment, insurance policies, first aid and emergency response practices.

Quality control process: the contractor should have a system or practices for guaranteeing quality work. This should include practices (such as tests) to ensure that only quality materials are used and close supervision by qualified professionals to ensure high quality workmanship.

Contact past clients or references: it is also important to hear from past clients of the contractor so as to know the experience they had and how the contractor handles issues should something happen not as expected.

Others: it is also important to find out on other issues such as lawsuits, bankruptcies, litigations, complaints and disputes that the contractor has been involved in and how they handled them. This helps to understand the level of professionalism of the contractor and how they handle issues when they arise.

The vetting process can also be done by creating a pre-qualification questionnaire or contractor vetting form and sending it to the prospective contractor for filling, or conducting an interview with the contractor’s representative.

Question 2

  1. Take off and bill of quantities

The unpriced bill of quantities for the building is as provided below

ITEMDESCRIPTIONUNITQUANTITYRATEAMOUNT
 EARTHWORKS AND EXCAVATIONS     
 Provide all materials and construct a machine cut dressed 2.5m high wall/fence around the boundary of the plotM2 375  
 Excavate top soil of the site average 200mm deep to remove top soil and cart and deposit 100m away and later spread and level on site as directedM2178  
 Excavate to reduce levels starting from stripped level and column pits not exceeding 1.5m deepM33.35  
 Trim and prepare bottoms of excavations to receive blindingM222.5  
 Remove surplus excavated material and cart awayM318.2  
 Return fill and compact selected excavated material around foundationsM312.6  
      
 Fillings     
 Supply and spread approved murram fillings to make up levels and compact well in 150mm thick layersM327  
 Supply 300mm thick approved hardcore filling, spread, level and compact well in 150mm thick layers to receive concrete surface bedM2178  
 Level and blind surface of hardcore with 50mm quarry duct to receive concrete surface bedM2178  
 Provide and apply approved anti-termite treatment to the  surface of blinded hardcore and surrounding areas in accordance with the manufacturer’s instructionsM2178  
      
 Mass concrete    
 Blinding: provide all materials, mix and place 50mm thick concrete grade C20/25 (1:3:6) for blinding under strip foundationsM222  
 Footing: provide all materials, mix, place, vibrate and compact concrete grade C30 (1:1.5:3)M33.35  
 Ground floor slab: provide all materials, mix, place, vibrate and compact 125mm thick concrete grade C25 (1:1.5:3) for ground slabM2178  
      
 Sawn formwork     
 Provide and fix sawn formwork to sides of strip foundationsM299  
 Provide and fix shuttering and formwork, including propping, strutting and striking, on sides of ground slabM259  
      
 Reinforcement     
 Provide fabric mesh reinforcement no. A142 mesh size 150 x 150mm (BRC) weighing 2.22kg/m2 and all other materials needed, including bends, tying wires and spacer blocks on floor slab.M2178  
 Provide deformed high yield steel Y12 barsKg88  
      
 Damp-proof course    
 Provide polythene damp-proof membrane, gauge 1000mm laid over hardcore with 300mm welted lapM2178  
 Provide bituminous felt damp-proof course under 200mm wide wallsM222.5  
      
 Foundation walling    
 Rough dressed natural stones and approved bedded and jointed in cement sand mortar (1:4): 225mm thick wallsM272  
      
 Plinths     
 12mm thick mortar cement and sand (1:4) rendered to plinthsM2178  
 Prepare and apply three coats of bituminous: dittoM2178  
      
      
 SUPERSTRUCTURE    
 WALLING    
      
 Brick walls bedded and jointed in cement and sand mortar (1:4) in:    
 305mm thick bricks/blocks for external walls reinforced with 32x2mm hoop iron every alternate courseM2158  
 100mm thick internal walls/partitions reinforced with 32x2mm hoop iron every alternate courseM2110  
 Provide 100mm pipe vents in beam above all doors with wire gauze and 25mmx400mm approximately above all windows as permanent ventilationNo7  
      
 Ring beam    
 Concrete class 20/20 for ring beamM39.0  
      
 Reinforcements     
 High yield Y12 reinforcement barsKg52  
 High yield Y8 reinforcement barsKg16  
      
 Formwork     
 Sawn formwork for lintels (ring beam)M2119  
      
 ROOF CONSTRUCTION    
 150×50 rafters (top member) and tie beamM90.5  
 100×50 strutsM25  
      
 Purlins     
 75×50 purlinsM6  
      
 Ridge board    
 225x25mm ridge boardM1  
      
 Wall plate    
 100×50 wall plateM2  
      
 Fascia board    
 200x25mm fascia boardM55  
      
 IT4 sheets    
 28 gauge roof covering sheets fixed onto timber purlinsM2162  
 Matching ridge cappingM140  
      
 DOORS    
 Wrot cypress    
 50mm thick single leaf panel door size 950x2100mm highNo7  
      
 Door frame and finishings    
 Wrot mahogany    
 Ex. 200x50mm rebated frameM25.4  
 50x25mm architraveM13.2  
 15mm quadrantM7.1  
      
 Ironmongery     
 Supply the following items with matching screw stall      
 100mm pressed steel butt hingesPcs14  
 Three lever mortice lock complete with set of lever handles with brass finishNo7  
 Rubber door stopNo7  
      
 Painting     
 Prepare and apply two undercoats and one finishing coat gloss oil paint to:    
 General wood surfacesM245  
 Wood surfaces 100-200mm girthM35  
      
 Prepare and apply aluminium wood primer to backs of wood before fixing them    
 Wood surfaces 100-200mm girthM35  
      
 WINDOWS    
      
 Supply and fix steel casement windows consisting of Standard Angline section frames and square rodes primed with one coat red oxide complete with steel metal hood permanent vents    
 Windows size 2200x1500mm highNO1  
 Ditto size 2100x1500mm highNO1  
 Ditto size 1800x1500mm highNO1  
 Ditto size 1700x1200mm highNO1  
 Ditto size 1200x1200mm highNO1  
 Ditto size 1000x500mm highNO1  
      
 Glazing     
 5mm thick clear sheet glass and glazing to steel metal casements with putty in panes 0.10-0.50 square metersM213.13  
      
 Window board    
 125x25mm windows board from Wrot cypressM34.8  
      
 Curtain rods    
 25mm diameter chrome curtain rodsM7.0  
 20mm diameter chrome curtain net rodsM4.8  
      
 Painting    
 Prepare and apply a layer of priming coat, two undercoats and one finishing coat gloss oil paint to glazed metal surfaceM212.5  
      
 FINISHES    
 INTERNAL WALL FINISHES    
 40mm thick cement sand render (1:4) to wallM2158  
 10mm thick cement screed to wallM2109.6  
      
 Painting     
 Prepare and apply three coats of first quality plastic emulsion paint to internal wallsM2267.6  
      
 EXTERNAL WALL FINISHES    
 40mm thick cement sand render (1:4) to ring beamM229.7  
      
 Painting     
 Prepare and apply three coats of first quality plastic emulsion paint to:    
 Ring beamM229.7  
      
 FLOOR FINISHES    
 40mm thick cement sand render (1:4) to floorM2178  
 5mm thick cement screed to floorM2178  
 Ditto, but 100mm high skirtingM99  
      
 CEILING FINISHES    
 Suspended ceilings    
 50x50mm brandering on trusses at 600mm c/c to receive ceiling boardM2178  
 12.5mm soft plasterboard suspended at height 2700mm above the finished floor levelM2178  
 CorniceM99  
      
 Painting     
 Prepare and apply three coats of first quality plastic emulsion paint to ceiling boardM2178  
      
 ELECTRICAL INSTALLATION WORKS    
 Allow PC sum of $3000 for electrical installation works (cables, lighting points and switches, lighting fittings, meter board and earthing)ItemLS  
      
 MECHANICAL WORKS    
 Allow PC sum of $5000 for mechanical works (kitchen sink, shower fittings, instant shower heater, bathroom shelf, curtain rail with shower curtains, towel rail, flexible tubing, water closet, CVPC pipes, bends/elbows, tees, reducers, threaded fittings and water storage tank)  ItemLS  
      
      
  • Schedule of rates for the substructure

The schedule of rate of the building up to the substructure level is provided below

ITEMDESCRIPTIONUNITQUANTITYRATE ($)AMOUNT ($)
 EARTHWORKS AND EXCAVATIONS     
 Provide all materials and construct a machine cut dressed 2.5m high wall/fence around the boundary of the plotM2 375207,500
 Excavate top soil of the site average 200mm deep to remove top soil and cart and deposit 100m away and later spread and level on site as directedM21782356
 Excavate to reduce levels starting from stripped level and column pits not exceeding 1.5m deepM33.35516.75
 Trim and prepare bottoms of excavations to receive blindingM222.5245
 Remove surplus excavated material and cart awayM318.27127.40
 Return fill and compact selected excavated material around foundationsM312.6563
      
 Fillings     
 Supply and spread approved murram fillings to make up levels and compact well in 150mm thick layersM32718486
 Supply 300mm thick approved hardcore fillings, spread, level and compact well in 150mm thick layers to receive concrete surface bedM21783.6640.80
 Level and blind surface of hardcore with 50mm quarry dust to receive concrete surface bedM21782356
 Provide and apply approved anti-termite treatment to the  surface of blinded hardcore and surrounding areas in accordance with the manufacturer’s instructionsM21783.5623
      
 Mass concrete    
 Blinding: provide all materials, mix and place 50mm thick concrete grade C20/25 (1:3:6) for blinding under strip foundationsM22210220
 Footing: provide all materials, mix, place, vibrate and compact concrete grade C30 (1:1.5:3)M33.353201,072
 Ground floor slab: provide all materials, mix, place, vibrate and compact 125mm thick concrete grade C25 (1:1.5:3) for ground slabM2178356,230
      
 Sawn formwork     
 Provide and fix sawn formwork to sides of strip foundationsM2994396
 Provide and fix shuttering and formwork, including propping, strutting and striking, on sides of ground slabM2593.5206.50
      
 Reinforcement     
 Provide fabric mesh reinforcement no. A142 mesh size 150 x 150mm (BRC) weighing 2.22kg/m2 and all other materials needed, including bends, tying wires and spacer blocks on floor slab.M217881,424
 Provide deformed high yield steel Y12 barsKg885440
      
 Damp-proof course    
 Provide polythene damp-proof membrane, gauge 1000mm laid over hardcore with 300mm welted lapM21785890
 Provide bituminous felt damp-proof course under 200mm wide wallsM222.5245
      
 Foundation walling    
 Rough dressed natural stones and approved bedded and jointed in cement sand mortar (1:4): 225mm thick wallsM272251,800
      
 Plinths     
 12mm thick mortar cement and sand (1:4) rendered to plinthsM21787.51,335
 Prepare and apply three coats of bituminous: dittoM21787.51,335
      
 Total carried to collection summary   25,607.45
  • Programme in form of Gantt chart

The Gantt chart for the building substructure is provided in the attached Excel file

References

2020ProjectManageent. Estimating your Project, 2020. 2020ProjectManagement,

https://2020projectmanagement.com/resources/cost-management/estimating-your-project (accessed November 24, 2020).

Belek, J. 8 Steps to vet construction subcontractors, 2017. https://srfm.com/business-insurance/8-

steps-to-vet-construction-subcontractors/ (accessed November 24, 2020). 

Ji Sae-Hyun, Ahn Joseph, Lee Hyun-Soo, & Han Kyeongjin. Cost Estimation Model Using

Modified Parameters for Construction Projects. Advances in Civil Engineering, 2019(1), 1-10.

Laryea, S. Impact of tendering procedure on price formation in construction contracts: case

study of the competitive negotiation procedure. Proceedings of WABER Conference, Accra, Ghana, 16-18 August 2017; University of the Witwatersrand, Johannesburg, 2017.

Varghese, S. & Kanchana, S. Modeling the parametric construction project cost estimate using

bootstrap and regression technique. International Journal on Engineering Technology and Sciences, 2(5), 47-50.