Question:
Discuss about the Project Proposal for Management?
Answer:
Introduction: (humankinetics, 2017), (wcastl, 2017) & (inspiriamedia, 2016)
Hobsons Bay City Council is involved in developing many play grounds and even few stadiums in Australia. It has many existing play grounds and is planning to build a new sports pavilion at Altona North (hobsonsbay, 2017).
During earlier days, all sports were being played on open ground. But due to increase in precision and demand of sports has raised the demand (Curbed, 2017) & (Worldstadiums, 2017). So the need for stadium building is vey a profitable business too. Few reasons to build stadium are:
Building the stadium creates opportunity for development of society
New spending for the construction of stadium increases circulation of currency in local market. It creates new opportunity of investment and help in expanding nearby business.
The group involved draws in voyagers and organizations to the host city
Increases local employment and improves social status of locals and cause new employment creator.
Discussion:
Assumptions: (Chinaculturetour, 2015) & (Securityinfowatch, 2003)
For developing the project schedule, few items we need to assume like:
The drawing provided with the tender shall not go under huge revision of scope of work.
Resources assumed shall be present throughout the project life cycle; any change in availability status may impact the project budget
Work Breakdown Structure of Stadium Construction:
High Level WBS is developed to capture the whole development activities. Level wise WBS is shown below for better understanding of scope of work.
Level 1:
WBS | Task Name |
1 | Hobsons Bay Stadium Project |
Level 2:
WBS | Task Name |
1 | Hobsons Bay Stadium Project |
1.1 | Initiation |
1.2 | Project Management |
1.3 | Execution |
1.4 | Closing |
Further WBS being divided in Level 3 (refer appendix A), 4 (refer Appendix B) is developed exclusively to further divide level 3 of Execution & the construction of level 4 in sub divided to Level 5 (refer Appendix C).
Gantt chart:
After detailing of WBS, the activities are punched exactly under each WBS to get bottom-up estimation of time. Below is the Gantt chart of Critical Path Method. Detailed
CPM with dates of all activities is mentioned in Appendix D.
Budgeting: Budget shall also be developed on WBS level wise. Also in future while tracking of expenses, the cost shall also be booked under that particular WBS to calculate the projects and track against baseline too.
High level Budget is:
Task Name | Duration | Start | Finish | Budget
(in AUD) |
|
Hobsons Bay Stadium Project | 320 days | Fri 5/12/17 | Thu 8/2/18 | 560,000 | |
Initiation | 20 days | Fri 5/12/17 | Thu 6/8/17 | 11,200 | |
Project Management | 30 days | Fri 6/9/17 | Thu 7/20/17 | 39,200 | |
Execution | 260 days | Fri 6/23/17 | Thu 6/21/18 | 504,000 | |
Closing | 30 days | Fri 6/22/18 | Thu 8/2/18 | 5,600 |
If we again further go down to further level and the entire detailed budget sheet is attached in Appendix E.
Now, by distributing the budget on calendar as per the schedule will develop a cash flow curve or the budgeted expenditure plan. This shall be as under:
Conclusion: (Stadiummouse, 2017), (Collegefootballtalk, 2014) & (Thesportseconomist, 2008)
With all this above study we can conclude that the stadium project can be an economically profitable to the sponsor along with the growth of society too. It is highly beneficial for the society by generating huge permanent job demand, increase motivation for local players, good entertainment business than silly television programs and also keep health right.
There is no age bar for using the facility. So, the return on investment can be easily obtained by organizing local and national level sports.
Appendix:
Appendix A: (WBS Level 3)
WBS | Task Name |
1 | Hobsons Bay Stadium Project |
1.1 | Initiation |
1.1.1 | Business proposal study |
1.1.2 | Analyis of SWOT |
1.1.3 | Stakeholder analysis |
1.1.4 | Assign Project Manager |
1.2 | Project Management |
1.2.1 | Define Scope Statement |
1.2.2 | Cost Management |
1.2.3 | Schedulling of Project |
1.2.4 | Commuinication Planning |
1.2.5 | Risk management |
1.2.6 | Procurement / Sub contract management |
1.2.7 | Quality Management |
1.3 | Execution |
1.3.1 | Engineering |
1.3.2 | Procurement |
1.3.3 | Construction |
1.4 | Closing |
1.4.1 | Obtaining feedback from all stakehlders |
1.4.2 | Check stakeholder’s satisfaction |
1.4.3 | Feedback analysis |
1.4.4 | Note Lessons learnt |
1.4.5 | Close Project |
Appendix B: (WBS Level 4)
WBS | Task Name |
1.3 | Execution |
1.3.1 | Engineering |
1.3.1.1 | Basic Plan sketch preparation |
1.3.1.2 | Detailing of floor plan |
1.3.1.3 | Finalisation of drainage system |
1.3.1.4 | Finalisation of Lightin system |
1.3.1.5 | Completion of all Engineering activities |
1.3.2 | Procurement |
1.3.2.1 | Floating of Request for Quotation |
1.3.2.2 | Evaluation of Bids |
1.3.2.3 | Finalisation of Sub-Contractor |
1.3.2.4 | Mobilisation at site |
1.3.2.5 | Ordering and supply of local purchase items |
1.3.2.6 | Ordering and supply of Special items |
1.3.3 | Construction |
1.3.3.1 | Start Construction work |
1.3.3.2 | Civil Work |
1.3.3.3 | Structural job |
1.3.3.4 | Mechanical erection work |
1.3.3.5 | Hydraulic Services |
1.3.3.6 | Electrical Work |
1.3.3.7 | Instrumentation Work |
1.3.3.8 | Finish work |
Appendix C: (WBS Level 5)
WBS | Task Name |
1.3.3 | Construction |
1.3.3.1 | Start Construction work |
1.3.3.2 | Civil Work |
1.3.3.2.1 | Site cleaning |
1.3.3.2.2 | Excavation for building foundations |
1.3.3.2.3 | Foundation work – concreting |
1.3.3.2.4 | Contruction of Storm water Channel system |
1.3.3.2.5 | Completion of all sub-structure work |
1.3.3.2.6 | Super-Structure Civil work |
1.3.3.3 | Structural job |
1.3.3.3.1 | Super-Structure Structural work |
1.3.3.3.2 | Install roof sheeting |
1.3.3.3.3 | Completion of all Structural job |
1.3.3.4 | Mechanical erection work |
1.3.3.4.1 | Supply and installation of Air conditioning System |
1.3.3.4.2 | Supply and installation of Toilet Exhaust System |
1.3.3.4.3 | Supply and installation of Ducts for the above systems |
1.3.3.4.4 | Completion of all Mechanical works |
1.3.3.5 | Hydraulic Services |
1.3.3.5.1 | Supply and install Sanitary Plumbing & Drainage system |
1.3.3.5.2 | Supply and install Cold and Hot water service |
1.3.3.5.3 | Supply and install Gas service |
1.3.3.5.4 | Completion of all Service Installation |
1.3.3.6 | Electrical Work |
1.3.3.6.1 | Cabling for all lighting work |
1.3.3.6.2 | Fixing lighting fixtures |
1.3.3.6.3 | Complete all electrical work |
1.3.3.7 | Instrumentation Work |
1.3.3.7.1 | Erect and Install all Panels, Diplays etc |
1.3.3.8 | Finish work |
1.3.3.8.1 | Landscaping |
1.3.3.8.2 | Checking all balance items |
1.3.3.8.3 | Complete all punch list items |
Appendix D:
WBS | Task Name | Duration | Start | Finish | Predecessors |
1 | Hobsons Bay Stadium Project | 320 days | Fri 5/12/17 | Thu 8/2/18 | |
1.1 | Initiation | 20 days | Fri 5/12/17 | Thu 6/8/17 | |
1.1.1 | Business proposal study | 10 days | Fri 5/12/17 | Thu 5/25/17 | |
1.1.2 | Analyis of SWOT | 5 days | Fri 5/26/17 | Thu 6/1/17 | 3 |
1.1.3 | Stakeholder analysis | 5 days | Fri 6/2/17 | Thu 6/8/17 | 4 |
1.1.4 | Assign Project Manager | 0 days | Thu 6/8/17 | Thu 6/8/17 | 5 |
1.2 | Project Management | 30 days | Fri 6/9/17 | Thu 7/20/17 | |
1.2.1 | Define Scope Statement | 10 days | Fri 6/9/17 | Thu 6/22/17 | 6 |
1.2.7 | Quality Management | 15 days | Fri 6/23/17 | Thu 7/13/17 | 8 |
1.3 | Execution | 260 days | Fri 6/23/17 | Thu 6/21/18 | |
1.3.1 | Engineering | 85 days | Fri 7/14/17 | Thu 11/9/17 | |
1.3.1.1 | Basic Plan sketch preparation | 20 days | Fri 7/14/17 | Thu 8/10/17 | 8,11,14 |
1.3.1.2 | Detailing of floor plan | 25 days | Fri 8/11/17 | Thu 9/14/17 | 17 |
1.3.1.3 | Finalisation of drainage system | 20 days | Fri 9/15/17 | Thu 10/12/17 | 18 |
1.3.1.4 | Finalisation of Lightin system | 20 days | Fri 10/13/17 | Thu 11/9/17 | 19 |
1.3.1.5 | Completion of all Engineering activities | 0 days | Thu 11/9/17 | Thu 11/9/17 | 20 |
1.3.2 | Procurement | 100 days | Fri 6/23/17 | Thu 11/9/17 | |
1.3.2.1 | Floating of Request for Quotation | 15 days | Fri 8/25/17 | Thu 9/14/17 | 18FF |
1.3.2.2 | Evaluation of Bids | 10 days | Fri 9/15/17 | Thu 9/28/17 | 23 |
1.3.2.3 | Finalisation of Sub-Contractor | 5 days | Fri 9/29/17 | Thu 10/5/17 | 24 |
1.3.2.4 | Mobilisation at site | 25 days | Fri 10/6/17 | Thu 11/9/17 | 25 |
1.3.3 | Construction | 180 days | Fri 10/13/17 | Thu 6/21/18 | |
1.3.3.1 | Start Construction work | 0 days | Thu 11/9/17 | Thu 11/9/17 | 21,26 |
1.3.3.2 | Civil Work | 105 days | Fri 11/10/17 | Thu 4/5/18 | |
1.3.3.2.1 | Site cleaning | 20 days | Fri 11/10/17 | Thu 12/7/17 | 30 |
1.3.3.2.2 | Excavation for building foundations | 10 days | Fri 12/8/17 | Thu 12/21/17 | 32,18 |
1.3.3.2.3 | Foundation work – concreting | 30 days | Fri 12/29/17 | Thu 2/8/18 | 33SS+15 days |
1.3.3.2.4 | Contruction of Storm water Channel system | 15 days | Fri 2/9/18 | Thu 3/1/18 | 34 |
1.3.3.2.5 | Completion of all sub-structure work | 0 days | Thu 3/1/18 | Thu 3/1/18 | 34,35 |
1.3.3.3 | Structural job | 65 days | Fri 3/2/18 | Thu 5/31/18 | |
1.3.3.3.1 | Super-Structure Structural work | 40 days | Fri 3/2/18 | Thu 4/26/18 | 36 |
1.3.3.3.2 | Install roof sheeting | 15 days | Fri 4/6/18 | Thu 4/26/18 | 39FF |
1.3.3.3.3 | Completion of all Structural job | 0 days | Thu 5/31/18 | Thu 5/31/18 | 40FF+25 days |
1.3.3.8 | Finish work | 55 days | Fri 4/6/18 | Thu 6/21/18 | |
1.3.3.8.2 | Checking all balance items | 5 days | Fri 6/1/18 | Thu 6/7/18 | 36,37,41,46,51,55,57 |
1.3.3.8.3 | Complete all punch list items | 10 days | Fri 6/8/18 | Thu 6/21/18 | 60 |
1.4 | Closing | 30 days | Fri 6/22/18 | Thu 8/2/18 | |
1.4.1 | Obtaining feedback from all stakehlders | 5 days | Fri 6/22/18 | Thu 6/28/18 | 61 |
1.4.2 | Check stakeholder’s satisfaction | 3 days | Fri 6/29/18 | Tue 7/3/18 | 63 |
1.4.3 | Feedback analysis | 2 days | Wed 7/4/18 | Thu 7/5/18 | 64 |
1.4.4 | Note Lessons learnt | 5 days | Fri 7/6/18 | Thu 7/12/18 | 65 |
1.4.5 | Close Project | 15 days | Fri 7/13/18 | Thu 8/2/18 | 66 |
Appendix E:
Task Name | Duration | Start | Finish | Budget
(in AUD) |
|
Hobsons Bay Stadium Project | 320 days | Fri 5/12/17 | Thu 8/2/18 | 560,000 | |
Initiation | 20 days | Fri 5/12/17 | Thu 6/8/17 | 11,200 | |
Business proposal study | 10 days | Fri 5/12/17 | Thu 5/25/17 | 5600 | |
Analyis of SWOT | 5 days | Fri 5/26/17 | Thu 6/1/17 | 2800 | |
Stakeholder analysis | 5 days | Fri 6/2/17 | Thu 6/8/17 | 2800 | |
Assign Project Manager | 0 days | Thu 6/8/17 | Thu 6/8/17 | 0 | |
Project Management | 30 days | Fri 6/9/17 | Thu 7/20/17 | 39,200 | |
Define Scope Statement | 10 days | Fri 6/9/17 | Thu 6/22/17 | 19600 | |
Quality Management | 15 days | Fri 6/23/17 | Thu 7/13/17 | 19600 | |
Execution | 260 days | Fri 6/23/17 | Thu 6/21/18 | 504,000 | |
Engineering | 85 days | Fri 7/14/17 | Thu 11/9/17 | 50400 | |
Basic Plan sketch preparation | 20 days | Fri 7/14/17 | Thu 8/10/17 | 10080 | |
Detailing of floor plan | 25 days | Fri 8/11/17 | Thu 9/14/17 | 25200 | |
Finalisation of drainage system | 20 days | Fri 9/15/17 | Thu 10/12/17 | 5040 | |
Finalisation of Lightin system | 20 days | Fri 10/13/17 | Thu 11/9/17 | 10080 | |
Completion of all Engineering activities | 0 days | Thu 11/9/17 | Thu 11/9/17 | 0 | |
Procurement / Sub-Contract | 100 days | Fri 6/23/17 | Thu 11/9/17 | 100800 | |
Floating of Request for Quotation | 15 days | Fri 8/25/17 | Thu 9/14/17 | 5040 | |
Evaluation of Bids | 10 days | Fri 9/15/17 | Thu 9/28/17 | 10080 | |
Finalisation of Sub-Contractor | 5 days | Fri 9/29/17 | Thu 10/5/17 | 10080 | |
Mobilisation at site | 25 days | Fri 10/6/17 | Thu 11/9/17 | 75600 | |
Construction | 180 days | Fri 10/13/17 | Thu 6/21/18 | 352800 | |
Start Construction work | 0 days | Thu 11/9/17 | Thu 11/9/17 | 0 | |
Civil Work | 105 days | Fri 11/10/17 | Thu 4/5/18 | 105840 | |
Site cleaning | 20 days | Fri 11/10/17 | Thu 12/7/17 | 28224 | |
Excavation for building foundations | 10 days | Fri 12/8/17 | Thu 12/21/17 | 14112 | |
Foundation work – concreting | 30 days | Fri 12/29/17 | Thu 2/8/18 | 42336 | |
Contruction of Storm water Channel system | 15 days | Fri 2/9/18 | Thu 3/1/18 | 21168 | |
Completion of all sub-structure work | 0 days | Thu 3/1/18 | Thu 3/1/18 | 0 | |
Structural job | 65 days | Fri 3/2/18 | Thu 5/31/18 | 176400 | |
Super-Structure Structural work | 40 days | Fri 3/2/18 | Thu 4/26/18 | 128291 | |
Install roof sheeting | 15 days | Fri 4/6/18 | Thu 4/26/18 | 48109 | |
Completion of all Structural job | 0 days | Thu 5/31/18 | Thu 5/31/18 | 0 | |
Finish work | 55 days | Fri 4/6/18 | Thu 6/21/18 | 70560 | |
Checking all balance items | 5 days | Fri 6/1/18 | Thu 6/7/18 | 23520 | |
Complete all punch list items | 10 days | Fri 6/8/18 | Thu 6/21/18 | 47040 | |
Closing | 30 days | Fri 6/22/18 | Thu 8/2/18 | 5600 | |
Obtaining feedback from all stakehlders | 5 days | Fri 6/22/18 | Thu 6/28/18 | 933 | |
Check stakeholder’s satisfaction | 3 days | Fri 6/29/18 | Tue 7/3/18 | 560 | |
Feedback analysis | 2 days | Wed 7/4/18 | Thu 7/5/18 | 373 | |
Note Lessons learnt | 5 days | Fri 7/6/18 | Thu 7/12/18 | 933 | |
Close Project | 15 days | Fri 7/13/18 | Thu 8/2/18 | 2800 |
References: (Harvard, 16 nos.)
HumanKinetics (2017). Economic impact of sport stadiums, teams, events. [Online]. Available at: http://www.humankinetics.com/excerpts/excerpts/economic-impact-of-sport-stadiums-teams-events (Accessed 12 May 2017).
Wcastl (2017). The Benefits of Stadium Lighting. [Online]. Available at: https://wcastl.org/the-benefits-of-stadium-lighting/ (Accessed 12 May 2017).
Inspiriamedia (2016). The 3 Amazing Benefits of Stadium Advertising. [Online]. Available at: https://www.inspiriamedia.com/blog/the-3-amazing-benefits-of-stadium-advertising (Accessed 12 May 2017).
Worldstadiums (2017). Stadium History. [Online]. Available at: http://www.worldstadiums.com/stadium_menu/architecture/historic_stadiums.shtml (Accessed 12 May 2017).
Curbed (2017). Introducing the stadium of the future, where technology is king. [Online]. Available at: https://www.curbed.com/2016/2/3/10942528/levis-stadium-technology-super-bowl-50-broncos-panthers (Accessed 13 May 2017).
Securityinfowatch (2003). An Introduction to Stadium and Arena Egress Design. [Online]. Available at: http://www.securityinfowatch.com/article/10592478/an-introduction-to-stadium-and-arena-egress-design (Accessed 13 May 2017).
Chinaculturetour (2015). National Stadium. [Online]. Available at: http://www.chinaculturetour.com/beijing/national-stadium.htm (Accessed 13 May 2017)
Thesportseconomist (2008). Stadium discussion. [Online]. Available at: http://thesportseconomist.com/2008/07/17/stadium-discussion/ (Accessed 13 May 2017).
Senate (2017). Stadium Discussion Points. [Online]. Available at: https://www.senate.mn/departments/scr/report/Stadium.htm (Accessed 13 May 2017).
Collegefootballtalk (2014). Syracuse sparks new stadium discussion. [Online]. Available at: http://collegefootballtalk.nbcsports.com/2014/01/25/syracuse-sparks-new-stadium-discussion/ (Accessed 13 May 2017).
Stadiummouse (2017). Conclusion. [Online]. Available at: http://www.stadiummouse.com/stadium/conclusion.html (Accessed 13 May 2017).
Hobsonsbay (2017). Home page. [Online]. Available at: http://www.hobsonsbay.vic.gov.au/Home (Accessed 13 May 2017).