Project management structure on: Work Based Structure

 Project management structure on: Work Based Structure

Work Based Structure (WBS)

University Assignment Help Australia

Work Breakdown Structure Template Guide Get Sample Assignment

Activity No. Activity / Task Duration Predecessor
1. Research the feasibility of the market1.1  Identify stakeholder involved1.2  Prepare the business case 

1.3  Create business case

3 days1 day1 day1 day 1.1 

1.2

2. Collect the information2.1 Develop management plan for action 1 day1 day 1.3
3. Scope Statement3.1 Fix Up meeting 1 day1 day 2.1
4. Design of the project 2 days 3.1
5. Execution of Project5.1 Site visit5.2 Survey5.3 Architectural

5.4 Landscaping

5.5 Site works execution

5.6 Project impact assessment

66 days5 days10 days20 days

20 days

6 days

5 days

45.15.2

5.3

5.4

5.5

6. Estimation & financial of the project6.1 Milestone review reports & meeting6.2 Overall project evaluation 120 days50 days70 days 6.1
7. 7.1 Marketing7.2 Sponsorship & Partnership7.3 Ad- Hoc Meetings 27 days20 days7 days 6.27.17.2
8. 8.1 Controlling8.2 Quality Control Issues8.3 Contingency Issues 10 days6 days4 days 7.38.18.2

 

Activity No. Activity/Task Duration Predecessor
1 Start the ProjectResearch the feasibility of the market1.1  Identify stakeholder involved1.2  Prepare the business case

 

1.3  Create business case

365 Days3 days1 day1 day

1 day

1.1 

1.2

2 Collect the information2.1 Develop management plan for action 1 day1 day 1.3
3 Scope Statement3.1 Fix Up meeting 1 day1 day 2.1
4 Design of the project 2 days 3.1
5 Execution of Project5.1 Site visit5.2 Survey5.3 Architectural

5.4 Landscaping

5.5 Site works execution

5.6 Project impact assessment

66 days5 days10 days20 days

20 days

6 days

5 days

45.15.2

5.3

5.4

5.5

6 Estimation & financial of the project6.1 Milestone review reports & meeting6.2 Overall project evaluation 120 days50 days70 days 6.1
7 7.1 Marketing7.2 Sponsorship & Partnership7.3 Ad- Hoc Meetings 27 days20 days7 days 6.27.17.2
8 8.1 Controlling8.2 Quality Control Issues8.3 Contingency Issues 10 days6 days4 days 7.38.18.2

 If you want Project management Assignment Help study samples to help you write professional custom essay’s and essay writing help.

Receive assured help from our talented and expert writers! Did you buy assignment and assignment writing services from our experts in a very affordable price.

To get more information, please contact us or visit www.myassignmenthelp.Com

                download-button                chat-new (1)